深基坑施工方案深基坑工程施工方案總工施工單位:編制日期:1深基坑施工方案目錄第一章編制依據...................................................................................................................101.1設計依據...................................................................................................................101.1.1設計、地勘及地區部門依據........................................................................101.2技術質量標準依據...................................................................................................101.2.1設計圖紙........................................................................................................101.2.2法律、法規、技術規范文件........................................................................10第二章工程概況...................................................................................................................112.1工程建設概況一覽表..............................................................................................112.2設計概況..................................................................................................................122.2.1建筑、結構設計概況...................................................................................122.3基坑工程概況..........................................................................................................132.3基坑圍護設計概況..................................................................................................142.4工程施工條件..........................................................................................................212.4.1工程水文地質狀況.......................................................................................212.4.2基坑周邊環境...............................................................................................24第三章施工安排...................................................................................................................253.1項目管理組織...........................................................................................................253.1.1項目管理組織機構.......................................................................................253.1.2項目管理機構及職責....................................................................................263.2項目管理目標..........................................................................................................283.3各項資源供應...........................................................................................................283.4施工流水段劃分及施工工藝流程..........................................................................283.4.1施工流水段劃分............................................................................................283.4.2施工工藝流程................................................................................................293.5施工現場總平面布置...............................................................................................323.5.1場地現狀條件及布置思路...........................................................................323.5.2場地平面布置...............................................................................................322深基坑施工方案3.5.3臨時用電量計算...........................................................................................323.6施工特點、重點和難點分析及應對措施...............................................................353.6.1圍護結構施工重點、難點分析及技術措施...............................................353.6.2周邊建筑物及管線安全的重點、難點分析及技術措施............................363.6.3安全文明管理重點、難點分析及技術措施................................................36第四章施工進度計劃...........................................................................................................374.1編制施工進度計劃依據...........................................................................................374.1.1工期要求........................................................................................................37第五章施工準備與資源配置計劃.......................................................................................375.1施工技術準備...........................................................................................................375.2勞動力需求計劃.......................................................................................................395.2.1圍護階段勞動力投入計劃............................................................................395.2.2降水施工階段勞動力投入計劃....................................................................395.2.3土方開挖施工階段勞動力投入計劃............................................................405.2.4圈梁及支撐施工階段勞動力投入計劃........................................................405.2.5勞動力選擇計劃............................................................................................405.3主要材料需求計劃...................................................................................................415.4施工機械、設備需要量計劃...................................................................................415.4.1基坑施工階段設備計劃................................................................................415.4.2主要測量設備投入計劃................................................................................42第六章施工方法及工藝技術...............................................................................................426.1測量施工方案及技術參數......................................................................................426.1.1測量準備........................................................................................................436.1.2主要測量儀器及性能....................................................................................436.1.3人員組織........................................................................................................446.1.4基準控制點(網).................................................................................446.1.5加密控制的布設原則及精度........................................................................446.1.6平面總控制網的建立....................................................................................456.1.7高程控制網的建立........................................................................................453深基坑施工方案6.1.8樁測量............................................................................................................466.1.9地下結構高程控制........................................................................................466.2雙輪銑施工方案......................................................................................................476.2.1CSM工法簡介及設計概況..........................................................................476.2.2施工工藝流程...............................................................................................476.2.3施工步驟.......................................................................................................476.2.4加固檢測.......................................................................................................516.2.5質量控制措施................................................................................................516.3支護鉆孔灌注樁施工方案......................................................................................526.3.1長螺旋鉆孔灌注樁施工工藝流程...............................................................526.3.2施工步驟........................................................................................................526.3.3施工重點難點分析與解決............................................................................556.4旋噴錨索施工方案..................................................................................................566.4.1旋噴錨索工藝原理.......................................................................................566.4.1旋噴錨索施工工藝流程...............................................................................566.4.2旋噴錨索施工操作要點...............................................................................576.4.3檢測技術與分析............................................................................................616.4.4質量控制標準................................................................................................626.5鋼格構立柱樁施工方案..........................................................................................636.5.1工藝流程.......................................................................................................636.5.2技術要求.......................................................................................................636.6壓頂圈梁、圍檁、連梁施工方案..........................................................................656.6.1施工工藝流程...............................................................................................656.6.2施工步驟.......................................................................................................666.6.3施工段劃分...................................................................................................676.6.4施工質量檢測及保證措施...........................................................................686.6.5拆撐施工.......................................................................................................686.7高壓旋噴樁施工方案..............................................................................................686.7.1高壓旋噴樁施工流程...................................................................................684深基坑施工方案6.7.2高壓旋噴樁施工要點...................................................................................696.7.3施工重點難點分析與解決...........................................................................696.7.4施工質量檢測與保障措施...........................................................................706.8履帶吊安裝施工方案..............................................................................................706.8.1施工流程.......................................................................................................706.8.2施工準備.......................................................................................................716.8.3安裝方法.......................................................................................................716.9基坑支撐施工及拆除施工方案..............................................................................726.9.1支撐工程簡述................................................................................................726.9.2鋼筋混凝土支撐施工....................................................................................726.9.3換撐及支撐梁拆除技術方案.......................................................................746.9.4換撐施工.......................................................................................................756.9.5支撐拆除控制原則.......................................................................................756.9.6換撐與支撐拆除勞動力與機械安排...........................................................756.10基坑監測施工方案................................................................................................756.10.1監測依據......................................................................................................756.10.2監測目的、原則和技術要求.....................................................................766.10.3監測點的布置及監測..................................................................................786.10.4監測儀器設備..............................................................................................816.10.5監測方法......................................................................................................836.10.6監測頻率......................................................................................................856.10.7報警控制值..................................................................................................866.10.8總包基坑監測措施.....................................................................................86基坑降水施工方案................................................................................................89降水井概況..................................................................................................896.11.2.施工工藝流程...........................................................................................896.11.3施工質量檢測及保證措施........................................................................926.11.4降水運營管理措施....................................................................................926.11.5降水對地面沉降影響與控制措施............................................................935深基坑施工方案6.11.6施工機械表................................................................................................936.12基坑開挖施工方案................................................................................................946.12.1基坑開挖工程概況.....................................................................................946.12.2土方開挖原則.............................................................................................946.12.3基坑開挖整體流程.....................................................................................956.12.4土方開挖分層方案.....................................................................................966.12.5施工方法.....................................................................................................976.12.6基坑土方收底施工方法.............................................................................986.13季節性施工方案.....................................................................................................98第七章各項管理計劃.........................................................................................................1097.1進度管理計劃.........................................................................................................1097.1.1確定施工進度控制點.................................................................................1097.1.2施工進度管理組織機構和職責分工.........................................................1097.1.3進度管理措施.............................................................................................1107.2質量管理計劃.........................................................................................................1117.2.1項目質量管理人員職責.............................................................................1117.2.2現場質量管理制度.....................................................................................1137.2.3確定質量控制點.........................................................................................1147.2.4現場質量管理制度.....................................................................................1147.2.5質量保證措施.............................................................................................1167.3安全管理計劃.........................................................................................................1207.3.1職業健康安全管理分解目標.............................................................................1207.3.2建立安全組織機構,明確安全職責和權限.............................................1207.3.3職業健康安全重大危險源.........................................................................1207.3.4職業健康安全資源配置計劃.....................................................................1207.3.5施工現場安全生產管理制度.....................................................................1217.3.6安全保證措施.............................................................................................1217.3.7消防保證措施.............................................................................................1237.3.8文明施工措施.............................................................................................1236深基坑施工方案7.3.9環保揚塵控制措施......................................................................................1247.4環境管理計劃.........................................................................................................1287.4.1環境管理目標.............................................................................................1287.4.2環境管理組織機構.....................................................................................1287.4.3辨識重大環境因素.....................................................................................1287.4.4環境保護資源配置計劃.............................................................................1297.4.5環境管理規章制度.....................................................................................1297.5資源節約管理計劃................................................................................................1307.5.1資源節約管理組織和職責、權限.............................................................1307.5.2資源節約管理規章制度.............................................................................1307.5.3資源節約保證措施.....................................................................................130第八章應急預案.................................................................................................................1318.1深基坑應急救援的任務和目標.............................................................................1318.1.1深基坑應急救援任務..................................................................................1318.1.2深基坑應急目標..........................................................................................1318.2本工程應急點概述.................................................................................................1318.3基坑安全狀況分析.................................................................................................1328.3.1基坑安全管理..............................................................................................1328.3.2基坑現狀分析..............................................................................................1328.4深基坑應急組織.....................................................................................................1328.4.1應急救援組織機構體系..............................................................................1328.4.2應急救援總指揮的職能及職責..................................................................1338.4.3應急組織副總指揮的職能及職責..............................................................1338.4.4應急救援小組及職責..................................................................................1338.5應急救援啟動程序.................................................................................................1368.5.1接警與通知..................................................................................................1368.5.2應急通訊聯系..............................................................................................1378.5.3啟動救援預案..............................................................................................1378.5.4警戒與治安..................................................................................................1377深基坑施工方案8.5.5人群疏散與安置..........................................................................................1378.6應急救援物資、器材和設備.................................................................................1378.7應急救援的培訓與演練.........................................................................................1388.7.1培訓..............................................................................................................1388.7.2應急演練......................................................................................................1398.8突發事故和緊急情況的處理措施.........................................................................1398.8.1止水帷幕漏水應急措施..............................................................................1398.8.2雙液注漿引水堵漏法。..............................................................................1398.8.3雙管雙向雙液旋噴法..................................................................................1408.8.4堆土加壓法..................................................................................................1408.8.5圍護樁系統受力和變形過大應急措施......................................................1418.8.6支撐體系受力和變形過大應急措施..........................................................1438.8.7邊環境沉降過大應急措施..........................................................................1438.8.8基坑周邊管線保護應急處理措施..............................................................1438.8.9基坑坑底隆起應急措施..............................................................................1448.8.10流砂與管涌應急措施................................................................................145坡頂沉降快、過大應急處理措施............................................................1458.8.12坡頂裂縫應急處理措施............................................................................1468.8.13突降大雨或暴雨應急處理措施................................................................1468.8.14坑內外水位變化過大應急處理措施........................................................1468.8.15基坑周邊建筑物傾斜應急處理措施........................................................1468.8.16自然災害應急處理措施............................................................................1468.8.17施工現場治安管理應急措施....................................................................1478.8.18施工現場交通事故應急措施....................................................................1478.8.19人員傷害安全事故的應急搶救方法........................................................1478.8.20基坑水位上升............................................................................................1498.8.21坍塌事故應急措施....................................................................................1498.9預案終止后恢復工作.............................................................................................151第九章附件.........................................................................................................................1528深基坑施工方案附件..............................................................................................................................................152附件:基坑周邊環境圖............................................................................................152附件:圍護施工階段平面布置圖............................................................................152附件:土方開挖路線圖............................................................................................152附件:土方開挖階段平面布置圖............................................................................152附件:圍護階段給排水平面布置圖........................................................................152附件:圍護階段臨電平面布置圖............................................................................152附件:基坑工程總進度計劃....................................................................................152附件:塔吊平面布置圖............................................................................................152附件:地勘報告......................................................................................................1529深基坑施工方案第一章編制依據1.1設計依據1.1.1設計、地勘及地區部門依據(1)《杭州富陽萬達廣場(南區)大商業巖土工程勘察報告》(詳細勘察階段)(2)業主提供地下管線資料、工程項目實地踏勘情況(3)《杭州市建設工程施工安全管理條例》1.2技術質量標準依據1.2.1設計圖紙建設單位2019年11月8日下發圍護結構設計圖紙,詳見表1.2-1。表1.2-1序號文件名稱編號類別1設計文件基坑支護設計圖紙201911支護設計1.2.2法律、法規、技術規范文件制性標準的有關文件,包括但不限于下表所列內容。表1.2-2主要技術標準和規范序號文件名稱編號類別1中華人民共和國建筑法年第46號主席令2中華人民共和國環境保護法2014年第9號主席令3中華人民共和國計量法--4建設工程質量管理條例2000年國務院第279號令法律5建設工程安全生產管理條例2003年國務院第393號令法規6杭州市建設工程質量監督管理辦法市政府令第195號7杭州市建設工程質量安全監督總站文件杭建監總[2008]62號8杭州市建設工程施工安全管理條例--10《危險性較大的分部分項工程安全管理規定》住建部【201837號令11規范《建筑地基基礎設計規范》GB50007-201112標準《混凝土結構設計規范》GB50010-201010深基坑施工方案13《鋼結構設計規范》GB50017-201714《工程測量規范》GB50026-200715《建筑結構荷載規范》GB50009-201216《建筑基坑工程監測技術規范》GB50497-200917《建筑地基基礎工程施工質量驗收標準》GB50202-201818《混凝土結構施工驗收規范》GB50204-201519《建設工程施工現場消防安全技術規范》GB50720-2011
20《建筑工程施工質量驗收統一標準》GB50300-201321浙江省標準《建筑工程基坑技術規程》DB33/T1096-2014地方22浙江省標準《建筑地基基礎設計規范》DB33/1136-2017標準23浙江省標準《基樁低應變動力檢測技術規程》DBJ10-4-9827《建筑基坑支護技術規程》JGJ120-201228《型鋼水泥土攪拌墻技術規程》JGJ/T199-201029《管井技術規范》GB50296-201430《建筑樁基技術規范》JGJ94-200831行業《建筑邊坡工程技術規范》GB50330-201332標準《建筑地基處理技術規范》JGJ79-201233《鋼筋焊接及驗收規程》JGJ18-201234《建筑施工安全檢查標準》JGJ59-201135《施工現場臨時用電安全技術規范》JGJ46-200536《建筑工程施工現場環境與衛生標準》JGJ146-201337技術中建八局《施工現場安全設施標準化圖集》--文件38《中建八局標準化手冊》2017年版39合同、招投標文件其他40其它相關規范及規程,如各規范有矛盾,以杭州市現行規范、規程為準。第二章工程概況2.1工程建設概況一覽表工程名稱富陽萬達廣場項目(36-E地塊大商業)工程性質商業建設規模總建筑面積116900建筑面積80000㎡,地下建筑面積36900㎡工程地址銀湖街道金橋北路東側,新橋新路北側11深基坑施工方案總占地面積44500㎡總建筑面積總建筑面積116900㎡建設單位杭州富陽萬達置業有限公司項目承包范圍BIM總包交鑰匙設計單位上海海洋地質勘察設計有限公司主要分包工程發包人提供的圖紙、招標文件、施工合同及工程量清單中內容勘察單位核工業湖州工程勘察院有限公司質量一次驗收合格率100%合同要監理單位上海三凱工程咨詢有限公司工期求2019年月20日計劃竣工日期:2020年3月10日工期總日歷天數:111日總包單位中國建筑第八工程局有限公司安全浙江省建筑安全文明施工標準化工地工程主要功能或用途商業2.2設計概況2.2.1建筑、結構設計概況項目內容建筑項目特征工程擬建筑物主要為商業樓,場地地下二層,局部地下一層,擬建筑物為框架結構,基礎擬采用樁基礎。建筑平面簡圖結構形式地下結構框架結構上部結構框架結構抗震等級抗震設防烈度為612深基坑施工方案2.3基坑工程概況1、擬建項目位于杭州富陽區,銀湖街道金橋北路東側,新橋新路北側。總建筑面積1169008000036900㎡。場地設二層地下室,局部地下一層。本工程采用φ700、φ800、φ900、φ1000直徑混凝土鉆孔灌注樁樁基礎形式。2、本次基坑支護范圍為本項目南地塊地下車庫。(1)2#地塊:基坑總面積為5.87萬平方米,基坑總周長1213.20m。其中商業區基坑面積2.51萬,基坑周長477.60m;住宅區基坑面積3.36萬平方米,基坑周長735.60m。3、圖中標高為建筑絕對標高,單位為米,尺寸單位為毫米。4、基坑場地周邊自然地坪絕對標高:基坑場地周邊自然地坪絕對標高為+8.50m;5、2#地塊大商業地下室結構標高和開挖深度(1)結構標高:①地下二層地庫區域:地下室底板面絕對標高為+0.80m,底板厚度為500mm,底板下設素墊層厚度②地下一層區域:地下室底板面絕對標高為+3.90m,底板厚度為400mm,底板下設素墊層厚度周邊柱墩承臺墊層底絕對標高為+3.22~-0.60m。(2)基坑開挖深度:①地下二層:至柱墩墊層底,基坑開挖深度為9.98~13.40m;②地下一層:至柱墩墊層底,基坑開挖深度為5.28~6.50m;③地下二層與地下一層高差為3.67~4.30m;基坑安全等級為二級;(3)基坑支護設計使用期限為24個月。7、在進行基坑施工前,應預先在現場放出基礎外輪廓線,使基坑內邊線與地下室外墻輪廓線保持不小于1000mm凈距,且與底板、坑邊承臺凈距不小于300mm。具體邊界以業主
提供的基坑開挖圖為準。若圖中尺寸與現場放樣不一致,以現場放樣為準。
8、基坑邊超載取值:a)基坑上口周邊范圍內不得堆載;b)2.0m范圍外至用地紅線內地面超載控制不大于20kPa;
c)周邊市政道路超載取30kPa;d)坑內高差部位超載取15kpa。通后,對相關部位需加強處理。13深基坑施工方案9、本項目高壓旋噴錨索施工要求:避免對管線產生不利影響。(2)本工程高壓旋噴錨索采用鉆孔、注漿、鋼鉸線跟進一次成形工藝。施工過程中需采取有效措施,控制成孔過程中及注漿后錨索孔位的冒水、冒砂等風險。中附錄A的要求進行基本實驗,基本試驗完成前,不得大面積施工錨索。(4)根據試樁情況,錨索在卵石(圓礫)層施工時,若施工難度較大,可采取跟管鉆進工藝施工;同時考慮到④層為承壓含水層,錨索施工時需采取相應的封堵措施。10、2#地塊項目施工順序:a)大商業基坑支護施工;b)住宅區基坑支護施工。抽出的地下水應排入市政管道或其它排水設施,避免回滲。2.3基坑圍護設計概況本基坑采用雙輪銑700內配φ3001m設置300×300范圍外至用地紅線內地面超載控制在20KPa,周邊市政道路超載取30KPa,坑邊高差部位超載取15KPa,施工前,施工單位應對坑邊局部堆場、塔吊、泵車停靠位置進行明確,與設計單位對該部位進行加強處理。具體情況如下(詳見附件2#地塊大商業基坑支護施工圖):B1′-B1′剖面區域采用網砼護坡+高壓旋噴錨索+鉆孔樁+CSM止水帷幕,坡頂采用厚C20一道在標高+6.3187.510.5傾角為155.5固段長9.514米,樁頂采用冠梁連接,CSM厚度為700mm,深度13.8米,水泥摻量25%。14深基坑施工方案B1-B1剖面圖(南區住宅基坑北側)B2-B2剖面區域采用網砼護坡+高壓旋噴錨索+鉆孔樁+CSM80厚C20標高+6.319830°166米,14連接,CSM厚度為700mm,深度13.8米,水泥摻量25%。B2-B2剖面圖(大商業北側B3-B3剖面區域采用網砼護坡+支護樁+立柱樁格構柱+CSM80厚C200.5灌注樁,樁長16.3米,樁頂采用冠梁連接,立柱和格構柱460×460角鋼4L140×140×1415深基坑施工方案深入底板底插入支護樁厚度為14與灌注樁之間采用柱間壓密注漿,長8.5m@1100。。B3-B3剖面圖(大商業-2F區域基坑西北角)B3′-B3′剖面區域采用網砼護坡+支護樁+立柱樁格構柱+CSM止水帷幕,護坡采用厚C20砼面層,配置φ6.5@250雙向配筋,φ50PVC管泄水孔,長米@2000,排樁為φ1000@1200灌注樁,樁長米,樁頂采用冠梁連接,立柱和格構柱460×460角鋼4L140×140×14深入底板底插入支護樁深,CSM厚度為700mm,深度14米,水泥摻量25%,CSM與灌注樁之間采用柱間壓密注漿,長11.5m@1200。B3′-B3′剖面圖(大商業-2F區域基坑西北角局部降板)16深基坑施工方案B4-B4剖面區域采用網砼護坡+雙排樁+CSM止水帷幕,坡頂土釘墻采用80厚C20砼面0.5灌注樁,樁長19.3米,外排φ1000@3600灌注樁,樁長19.3m,樁頂采用1200×800@3600連梁連接,CSM厚度為700mm,深度14.5米,水泥摻量25%,CSM與灌注樁之間采用柱間壓密注漿,長8.5m@1100。。B4-B4剖面圖(基坑西側北段-2F區域)B5-B5剖面區域采用網砼護坡+雙排樁+CSM止水帷幕,坡頂土釘墻采用80厚C20砼面0.5灌注樁,樁長13.2米,外側為φ700@3000灌注樁,樁長13.2m,樁頂采用800×700@3000的連梁連接,CSM700mm,深度14.5米,水泥摻量25%,CSM與灌注樁之間采用柱間壓密注漿,長4.5m@1000。17深基坑施工方案B5-B5剖面圖(基坑西側南段商業區-1F區域)B5′-B5′剖面區域采用網砼護坡+雙排樁+CSM80厚C20砼0.517.31000×800@3300的連梁連接,CSM700mm,深度14.5米,水泥摻量25%,CSM與灌注樁之間采用柱間壓密注漿,長8m@1100。18深基坑施工方案B5′-B5′剖面圖(基坑西側南段商業區-1F區域集水井部位)B6-B6剖面區域采用網砼護坡+支護樁+立柱樁格構柱+CSM80厚C200.5灌注樁,樁長11.7米,樁頂采用冠梁連接,立柱和格構柱460×460角鋼4L140×140×14深入底板底插入支護樁深,CSM厚度為700mm,深度14米,水泥摻量25%。B6-B6剖面圖(基坑南側-1F區)19深基坑施工方案B7-B7剖面區域采用網砼護坡+臨時放坡+高壓旋噴重力壩,坡頂土釘墻采用80厚C200.52400寬200厚C20置φ10@200雙向配筋。從基坑底+2.72采用1:1.5放坡至坑頂,+5.5處設置一道3米寬平臺。B7-B7剖面圖(大商業-1F與住宅交界區域)B8-B8剖面大商業-1F與-2F高差部位旋噴樁φ600@450,樁長8.5m,水泥摻量25%,,樁頂采用2400寬厚C20砼面層,配置φ10@200雙向配筋。B9-B9剖面大商業-2F與住宅交界部位采用大放坡開挖,坡面采用80厚砼面層,配置φ6.5@2500.51:1放坡至+1.50留置3米寬平臺、1:2放坡至+5.00處留置一道3米寬平臺后1:1.5放坡至基坑頂。20深基坑施工方案基坑降水疏干井73140.70.3井13口,井深140.7米,井管直徑0.3米。降水井平面布置圖詳見附件。2.4工程施工條件2.4.1工程水文地質狀況1.氣象水文條件氣象臺資料,富陽市常年平均氣溫年8月4端最低氣溫-14.4℃(1977年1月5日)。年平均降雨量1432.6mm,每年有兩個雨季,4~6年月6日20:00~7日臺風“菲特”影響降雨),1小時最大降雨量77.6mm(1987.4.5.2)。多年平均蒸發量1252.8mm,相對濕度78%,區內日照充足,全年無霜期250天左右。全年風向1.3-2.4m/s。季節變化明顯。勘察區東側為新橋浦,新橋浦河道寬約20~35m,水流通暢,場地地下水實測地下水位埋深在1.2~5.00m,新橋浦河水水位標高+5.697.93~7.958.46~8
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯系上傳者。文件的所有權益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網頁內容里面會有圖紙預覽,若沒有圖紙預覽就沒有圖紙。
- 4. 未經權益所有人同意不得將文件中的內容挪作商業或盈利用途。
- 5. 人人文庫網僅提供信息存儲空間,僅對用戶上傳內容的表現方式做保護處理,對用戶上傳分享的文檔內容本身不做任何修改或編輯,并不能對任何下載內容負責。
- 6. 下載文件中如有侵權或不適當內容,請與我們聯系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 行政管理專科經濟法試題解析及答案
- 肆虐傳染病的護理措施試題及答案
- 2025年護士執業考試的重要性題及答案
- 護士資格考試知識點試題及答案
- 藥物安全教育的重要性分析試題及答案
- 2025年行政管理語文考試的挑戰性試題與答案
- 經濟法概論綜合復習試題及答案
- 行政法學的未來挑戰與試題答案探討
- 新時代的文化挑戰試題及答案
- 冀教版六年級下冊數學全冊課時練習含答案
- 2025年高考作文素材積累之4月時事熱點及時評
- 2025年四川省自然資源投資集團有限責任公司招聘筆試參考題庫含答案解析
- 2025重慶機場集團限公司公開招聘46人易考易錯模擬試題(共500題)試卷后附參考答案
- 2025年浙江省寧波市一模科學試卷
- 初中數學融入課程思政的路徑探索
- 《Python數據可視化》全套教學課件
- GB 29743.2-2025機動車冷卻液第2部分:電動汽車冷卻液
- 河南省南陽市六校2024-2025學年高二下學期4月期中考試語文試卷(圖片版含答案)
- 安全伴我行-筑牢生命防線
- 通訊遷改合同協議
- 土地合同轉讓三方協議書
評論
0/150
提交評論