1、蘭州新區(qū)法院審判庭工程冬期施工方案中國十九冶蘭州新區(qū)法院項目部二0一六年十月二十五日目 錄一、編制依據(jù)·········································
2、83;··········1二、工程概況······································
3、183;············2三、冬施概況····································&
4、#183;··············2四、冬期施工部署·································
5、3;·············3五、冬期施工準(zhǔn)備···································&
6、#183;···········7六、冬期施工主要措施····································
7、183;·····10七、施工質(zhì)量要求··········································
8、3;···18八、安全措施·············································
9、183;····19九、消防及環(huán)保措施···········································
10、83;20十、冬施期保溫材料的準(zhǔn)備·····································21十一、冬季施工砼的熱工計算·······
11、3;·····························22十二、應(yīng)急預(yù)案···················&
12、#183;····························2327一、編制依據(jù) 1. 蘭州新區(qū)法院審判庭項目工程施工圖。2.建筑地基基礎(chǔ)工程施工工藝規(guī)程Q/GJZ01-20053.建筑地基基礎(chǔ)工程施工質(zhì)量驗收規(guī)范GB50202-20024.混凝土結(jié)構(gòu)工程施工規(guī)范GB50666-20115.混凝土結(jié)構(gòu)工程施工質(zhì)量
13、驗收規(guī)范GB50204(2011年版)6.混凝土泵送施工技術(shù)規(guī)程JGJ/T10-20117.混凝土外加劑應(yīng)用技術(shù)規(guī)范GB50119-2003 8.建筑工程冬期施工規(guī)程(JGJ/T104-2011)9. 施工現(xiàn)場臨時用電安全技術(shù)規(guī)范JGJ46-200510. 甘肅省、地(市)現(xiàn)行的有關(guān)施工規(guī)定和文件。11.建筑工程施工質(zhì)量驗收統(tǒng)一標(biāo)準(zhǔn)(GB503002001); 12.地下防水工程質(zhì)量驗收規(guī)范(GB502082002); 13.地下防水工程技術(shù)規(guī)范(GB501082001);14. 建筑施工手冊第四版 15.我司有關(guān)項目法施工管理辦法及質(zhì)量、技術(shù)、安全等管理文件。16.我司按照GB/T19001
14、-2008 idt ISO9001:2008質(zhì)量管理體系要求、GB/T28001-2001職業(yè)健康安全管理體系規(guī)范、GB/T24001-2004 idt ISO14001:2004環(huán)境管理體系要求及使用指南、GB/T50430-2007工程建設(shè)施工企業(yè)質(zhì)量管理規(guī)范建立的“四標(biāo)一體”管理體系。16.1質(zhì)量、職業(yè)健康安全和環(huán)境管理手冊16.2質(zhì)量、職業(yè)健康安全和環(huán)境程序文件17. 本公司機(jī)械設(shè)備狀況、人員狀況及成熟可靠的施工技術(shù)和豐富的同類建筑工程施工經(jīng)驗。二、工程概況本工程為蘭州新區(qū)法院審判庭,該工程項目場地位于蘭州新區(qū)中川鎮(zhèn)。該工程結(jié)構(gòu)形式為框架結(jié)構(gòu),結(jié)構(gòu)單元為地下一層、地上五層,基礎(chǔ)形式為樁
15、-承臺基礎(chǔ)。目前形象進(jìn)度為正在進(jìn)行基礎(chǔ)部分施工。為了確保工程質(zhì)量、保證工程進(jìn)度,特編制本方案。三、冬施概況 3.1 冬期施工期限的劃分根據(jù)建筑工程冬期施工規(guī)程(JGJ104-2011)的規(guī)定,室外日平均氣溫連續(xù)5天穩(wěn)定低于5即進(jìn)入冬期施工;當(dāng)室外日平均氣溫連續(xù)5天穩(wěn)定高于5 時解除冬期施工。一般規(guī)定每年11月15日至次年3月15日為冬季施工階段。按溫度不同又可劃分為初冬、嚴(yán)冬、寒冬三個階段:平均氣溫為0,最低溫度在-5左右為初冬階段,一般在11月15日11月30日;平均氣溫為-5,最低溫度低于-10為嚴(yán)冬,一般在12月1日12月20日;平均氣溫為-10,最低溫度達(dá)到-15為寒冬,一般在12月2
16、1日次年元月20日。應(yīng)按不同溫度階段采用不同施工方法,以及采用合理有效的冬施措施,以確保降低成本,提高工程施工質(zhì)量。3.2 冬施期施工進(jìn)度計劃本工程在冬期施工部位主要為±0.000以上的主體結(jié)構(gòu)施工任務(wù)。3.3 冬施期主要施工內(nèi)容及施工流程施工準(zhǔn)備與測量定位放線鋼筋綁扎模板支設(shè)混凝土澆筑覆蓋保溫養(yǎng)護(hù),一層到五層。四、施工部署4.1 冬期施工原則根據(jù)本工程所處的地理位置和工期要求并結(jié)合目前本工程的實際情況及特點,該工程冬期施工的原則:認(rèn)真貫徹執(zhí)行國家的技術(shù)經(jīng)濟(jì)政策,做到技術(shù)先進(jìn)、經(jīng)濟(jì)合理、安全適用、確保冬季施工質(zhì)量。4.2 冬期施工組織措施4.2.1 組織有關(guān)人員學(xué)習(xí)冬施方案,并向班組
17、交底。4.2.2 進(jìn)入冬期施工前,對測溫、保溫人員專門組織技術(shù)培訓(xùn),學(xué)習(xí)工作范圍內(nèi)的有關(guān)知識,明確職責(zé),經(jīng)考試合格后,方準(zhǔn)持證上崗。4.2.3 項目部成立冬季施工領(lǐng)導(dǎo)小組,負(fù)責(zé)組織冬季施工的生產(chǎn)、技術(shù)、質(zhì)量、安全管理和冬施物資的供應(yīng),負(fù)責(zé)冬施的工作的協(xié)調(diào)組織,并明確責(zé)任,確保冬季施工中,各項工作及時有效的進(jìn)行,避免由于冬季施工組織不力給生產(chǎn)進(jìn)度、工程質(zhì)量、安全施工造成影響。4.2.4 安排包豐滿、王彪進(jìn)行氣溫觀測并做好記錄,與當(dāng)?shù)貧庀笳颈3致?lián)系,及時接收天氣預(yù)報,防止寒流襲擊。現(xiàn)場設(shè)置溫度計,隨時做好測溫。4.2.5 冬季施工領(lǐng)導(dǎo)機(jī)構(gòu):為確保今年的冬期施工順利進(jìn)行,認(rèn)真組織落實冬期措施,按期保
18、質(zhì)保量完成施工生產(chǎn)任務(wù),項目部給予足夠重視,成立以項目經(jīng)理為首的冬期施工領(lǐng)導(dǎo)小組。組 長:田健強(qiáng)副組長:楊興志成 員:包鋒滿,王彪。4.2.6 領(lǐng)導(dǎo)小組成員職責(zé)范圍:組長由項目經(jīng)理田健強(qiáng)擔(dān)任,統(tǒng)一對冬季施工的總體指揮。副組長 :楊興志,負(fù)責(zé)冬季施工中施工生產(chǎn)的有序進(jìn)行;協(xié)調(diào)施工生產(chǎn)中各工序的銜接,保證施工進(jìn)度,確保冬季施工正常進(jìn)行;負(fù)責(zé)冬季施工中所有技術(shù)問題的處理,對冬季施工中可能出現(xiàn)的技術(shù)問題提前加以解決,保證冬季施工中不因技術(shù)問題影響工程的施工質(zhì)量;成員: 包鋒滿 負(fù)責(zé)冬季施工中各項工序的質(zhì)量監(jiān)督,各項技術(shù)準(zhǔn)備,做好冬季施工中各分部分項工程的技術(shù)交底,為冬季施工做好技術(shù)支持;成立工程質(zhì)量及
19、安全領(lǐng)導(dǎo)小組, 王彪 為組長、成員 王俊德,王晉 ,郭建輝負(fù)責(zé)冬季施工生產(chǎn)的安全監(jiān)督。此外項目部總結(jié)往年冬季施工的經(jīng)驗,利用好目前尚處于常溫施工的好時機(jī),抓緊做好現(xiàn)場各方面的準(zhǔn)備工作,保證冬施工作的順利進(jìn)行。小組成員負(fù)責(zé)冬施工作的協(xié)調(diào)組織,并明確責(zé)任,確保冬季施工中,各項工作及時有效進(jìn)行。4.2.7 人員培訓(xùn)為確保冬期施工質(zhì)量,達(dá)到施工進(jìn)度要求,冬期施工前必須進(jìn)行冬期施工技術(shù)培訓(xùn)。4.2.7.1 冬期施工技術(shù)培訓(xùn)的主要內(nèi)容:學(xué)習(xí)國家和地方有關(guān)冬期施工規(guī)范、標(biāo)準(zhǔn)、規(guī)定,學(xué)習(xí)建筑工程冬期施工規(guī)程學(xué)習(xí)有關(guān)的冬期施工基本理論知識及施工方法,了解其適用條件及可預(yù)期達(dá)到的效果;學(xué)習(xí)和理解本工程的冬期施工方
20、案,單項工程的施工組織設(shè)計或技術(shù)措施。4.2.7.2 經(jīng)培訓(xùn)的施工現(xiàn)場管理人員和技術(shù)人員應(yīng)掌握的工作要點:了解當(dāng)天和數(shù)日的天氣預(yù)報,測溫人員提供測溫報告,對天氣突變時能做出防范措施;掌握所采用的施工方法技術(shù)要點,操作程序,質(zhì)量要求;根據(jù)砼養(yǎng)護(hù)的測溫記錄,推算砼強(qiáng)度的增長情況。根據(jù)同條件養(yǎng)護(hù)試塊的試壓結(jié)果推定砼是否達(dá)到臨界強(qiáng)度,以及確定砼的拆模時間及拆模后的外表面是否需要保溫及養(yǎng)護(hù)措施;檢查施工的各部位的保溫、防護(hù)措施的實施情況;檢查冬期施工的熱源設(shè)備運行情況。檢查冬期施工的安全措施,特別是重點部位,如電氣設(shè)備、使用明火部位、易燃易爆材料、化學(xué)外加劑材料、電焊、氣焊設(shè)備等是否有違章情況;4.3
21、冬施期對臨時管線、管溝布置要求 4.3.1 冬期施工前,認(rèn)真查看現(xiàn)場布置情況、臨水臨電布置情況,作好現(xiàn)場臨時供水管道的保溫防凍工作,將現(xiàn)場內(nèi)所有供水管路全部埋入地下0.5m并做好保溫,外露部分做好保溫、防凍工作。不用時應(yīng)臨時放空,避免凍裂,影響施工。4.3.2 冬期施工前,由項目經(jīng)理組織對該工程安全、設(shè)備、所需材料在冬施期的施工準(zhǔn)備情況和現(xiàn)場場地條件等內(nèi)容進(jìn)行檢查。冬期施工要用的各種機(jī)械設(shè)備(包括電焊機(jī)、電纜)等方面進(jìn)行詳細(xì)的檢查,對于發(fā)現(xiàn)的問題應(yīng)立即組織人員進(jìn)行整改。4.3.3 依據(jù)工作量提前組織好有關(guān)機(jī)具、保溫材料及產(chǎn)熱設(shè)備4.3.4 通知攪拌站提前做好冬期施工砼及外加劑的試配工作,嚴(yán)格按
22、照試驗室出具的混凝土施工配合比,并搭設(shè)保溫棚,保證攪拌站工作溫度,在混凝土運輸過程中對混凝土罐車進(jìn)行保溫。4.4 對項目部辦公生活區(qū)及分包生活區(qū)的檢查和安排 冬季施工期間由項目經(jīng)理組織定時對項目部現(xiàn)場辦公區(qū)及生活區(qū)設(shè)施進(jìn)行檢查并及時進(jìn)行整改。4.5 冬期施工工作重點4.5.1 經(jīng)常組織各組員及其他有關(guān)人員學(xué)習(xí)冬施相關(guān)技術(shù)質(zhì)量要求,了解冬施的重要性。4.5.2 在冬施期間,安排專人了解氣象信息,并負(fù)責(zé)將天氣情況及時反饋給有關(guān)人員,為防寒保溫工作做準(zhǔn)備。4.5.3 項目部對各專業(yè)班組認(rèn)真作好技術(shù)、安全交底,將冬施對工程的影響減少到最小程度。五、冬期施工準(zhǔn)備5.1 施工技術(shù)準(zhǔn)備5.1.1 認(rèn)真熟悉、
23、學(xué)習(xí)、審核施工圖紙,透徹領(lǐng)會設(shè)計意圖, 對進(jìn)入冬期施工的工程項目,進(jìn)行全面的調(diào)研,掌握真實的數(shù)據(jù),為冬期施工提供必要的依據(jù)。 5.1.2 冬施前應(yīng)根據(jù)施工方案和有關(guān)規(guī)范要求對施工人員做好冬期施工的培訓(xùn)教育工作沒特別應(yīng)加強(qiáng)對測溫人員、特殊工種人員的培訓(xùn),使冬期施工人員對冬期施工的技術(shù)要點及安全。消防注意事項做到心中有數(shù),確保冬期施工的正常進(jìn)行。進(jìn)入冬期施工前,應(yīng)對摻加外加劑人員、測溫人員等有關(guān)人員進(jìn)行技術(shù)業(yè)務(wù)培訓(xùn),學(xué)習(xí)本工作范圍內(nèi)的有關(guān)知識,明確職責(zé),經(jīng)考試合格后,方準(zhǔn)上崗工作。 5.1.3 對測溫人員進(jìn)行培訓(xùn)交底,主要工作內(nèi)容為大氣測溫和混凝土養(yǎng)護(hù)測溫工作,達(dá)到混凝土測溫的真實性 ,
24、為混凝土的養(yǎng)護(hù)提供科學(xué)依據(jù)。 5.1.4 對主要使用的材料進(jìn)行交底,準(zhǔn)備保溫及加溫材料。5.2施工準(zhǔn)備 5.2.1 施工前準(zhǔn)備 非外露水管均埋入地面以下0.5米。外露用水管周圍進(jìn)行覆蓋保溫,封閉暫不用水龍頭,冬施用的水龍頭安裝回水裝置和保溫,不得有常流水現(xiàn)象。 5.2.2 總平面布置與臨時管線、管溝進(jìn)入冬期施工前,認(rèn)真查看施工總平面圖、平面臨水布置圖及相關(guān)資料,了解各類臨時地下管線、管溝平面位置及標(biāo)高,針對臨時用水及消防栓找出需要加深的地下管線、需要保溫的地上管線及要保溫的管溝等進(jìn)行保溫。 5.2.3 生活安排 項目辦公區(qū)、生活區(qū)采用電暖氣取暖,在工人宿舍增加被褥和御寒衣服。5.3材料資源準(zhǔn)備
25、 5.3.1 現(xiàn)場材料按指定位置碼放整齊,材料必須架空距地不小于300mm,鋼筋下墊枕木,鋼筋堆放高度應(yīng)小于2m。 5.3.2 竹膠板下將堆放地面夯實并采用木方墊高,同時對模板進(jìn)行覆蓋,防止雨淋、水泡導(dǎo)致無法使用。 5.3.3 提前準(zhǔn)備好塑料薄膜、麻袋或草簾被等冬施必備物資。材料準(zhǔn)備計劃表序號名稱規(guī)格數(shù)量單位用途1塑料地膜20000混凝土覆蓋保溫2棉被6000混凝土覆蓋保溫3雙層彩條布3000擋風(fēng)保溫措施4防寒毛氈5000覆蓋保溫5炭爐子廢油桶加工50個現(xiàn)場保溫6無煙煤炭500噸現(xiàn)場保溫7防寒大衣130 件勞保8溫度計-30100100支室外測溫9電阻測溫儀2臺測溫10埋入式溫度計4
26、6支電子測溫儀配套溫度計11紅外線測溫儀1臺測混凝土出罐溫度及入模溫度13電暖氣10臺宿舍及辦公室取暖14醫(yī)療用品2000元備用15早強(qiáng)防凍劑kg16混凝土試模6組17腳手板200塊為保溫材料負(fù)重防止被風(fēng)吹起188#鐵絲,釘子19千瓦燈20架現(xiàn)場照明用20行走燈22個管理人員、值班人員使用5.4安全工作準(zhǔn)備 5.4.1 項目部安全領(lǐng)導(dǎo)小組針對冬施制訂安全規(guī)章制度,落實責(zé)任,并定期組織安全檢查。 5.4.2 冬施之前,對工人及作業(yè)人員組織安全交底,明確注意事項。5.4.3 對塔吊要定期觀測沉降及偏差,尤其在大風(fēng)或雨雪后做好觀測記錄,發(fā)現(xiàn)問題及時進(jìn)行處理。 5.4.4 現(xiàn)場用電必須按照施工現(xiàn)場臨時
27、用電安全技術(shù)規(guī)范JGJ46-2005的規(guī)定實施,在冬施前對現(xiàn)場所有動力及照明線路、供配電設(shè)施進(jìn)行一次全面檢查,對線路老化、安裝不良及漏電現(xiàn)象及時修理和更換,嚴(yán)禁帶隱患使用。 5.4.5 室外配電箱、開關(guān)箱及用電機(jī)具等采取防雨、防潮、防雷、防雪等措施,外殼要做接地保護(hù),有問題及時排除并作好相應(yīng)記錄。 5.4.6 建立安全值班及通報制度,遇有緊急情況要及時通報各級領(lǐng)導(dǎo)。六、冬期施工主要措施6.1模板工程6.1.1根據(jù)施工的實際情況盡可能延長拆模時間以便增加混凝土正溫養(yǎng)護(hù)時間。6.1.2 冬期施工,對于模板的拆除,進(jìn)行申請,經(jīng)過項目技術(shù)主管允許批準(zhǔn)后方可進(jìn)行模板拆除。粱、板底模拆除時砼強(qiáng)度必需依照圖
28、紙規(guī)范,同條件試塊強(qiáng)度為拆模依據(jù)。6.1.3 支模時,將模板上的冰雪和泥土清除干凈,方可使用。在支模完成后,必須將模板內(nèi)雜物、冰雪清掃干凈,模板不準(zhǔn)澆水。6.1.4 模板和保溫層在砼達(dá)到要求強(qiáng)度并冷卻到5后方可拆模,拆模時,砼表面與環(huán)境溫差大于20時,拆模后的砼表面加臨時覆蓋,使其緩慢冷卻。拆模以同條件試塊的抗壓強(qiáng)度為依據(jù)。拆模在白天氣溫較高時進(jìn)行,若遇冷氣流,停止拆模施工。6.1.5 在負(fù)溫條件下嚴(yán)禁澆水養(yǎng)護(hù)。拆模后及時覆蓋塑料薄膜,上加麻袋或草簾被進(jìn)行保溫覆蓋養(yǎng)護(hù)。6.2鋼筋工程 6.2.1 在負(fù)溫條件下使用的鋼筋,施工時加強(qiáng)檢驗,鋼筋在運輸和加工過程中防止撞擊和刻痕。鋼筋工程主要注意在冬
29、施期間對成品、半成品用草簾被覆蓋保溫。 6.2.2 鋼筋加工在加工棚內(nèi)進(jìn)行,加工完的鋼筋放置避開雨、雪地,下部用墊塊或方木墊起100mm以上,防止受潮或粘污。 6.2.3 冬期鋼筋施工階段,雪后及時清理施工完畢鋼筋表面積雪,防止鋼筋銹蝕。施工前搭設(shè)人行馬道,不得在鋼筋架上行走,防止鋼筋變形,人員摔傷。遇下雪天氣綁扎鋼筋,綁扎好地部分加蓋塑料布,減少積雪清理難度。 6.2.4 調(diào)直鋼筋符合以下規(guī)定:采用冷拉方法調(diào)直鋼筋時,級鋼筋的冷拉率不宜大于4;其環(huán)境溫度不低于-20;當(dāng)溫度低于-25時,不得對HRB400級的鋼筋進(jìn)行冷彎操作,以避免在鋼筋彎點處發(fā)生強(qiáng)化,造成鋼筋脆斷。6.3 混凝土工程本工程
30、現(xiàn)場澆筑砼采用商品砼,底板及剪力墻為C40P8砼,地上為C40、C35、C30要求攪拌站提前做好該強(qiáng)度冬期砼的試配,砼中摻加早強(qiáng)型的復(fù)合防凍劑,為保證砼質(zhì)量,在嚴(yán)寒天氣不進(jìn)行砼的澆筑施工,項目部應(yīng)與商砼供應(yīng)站及時做好協(xié)調(diào)工作。我施工單位已與商砼供應(yīng)站技術(shù)質(zhì)量部取得聯(lián)系,明確了保證砼施工質(zhì)量供求雙方的權(quán)利和義務(wù),商砼供應(yīng)站技術(shù)質(zhì)量部出具了預(yù)拌混凝土冬期施工質(zhì)量保證措施文件.。6.3.1 砼材料要求 a、拌和物所用的骨料等必須符合冬施的各項要求,優(yōu)先采用加熱水的方法,當(dāng)加熱水仍不能滿足要求時,再對骨料進(jìn)行加熱。水溫控制在50±5,水泥不得直接加熱,使用前宜運入暖棚內(nèi)存放。 b、
31、水泥采用普通硅酸鹽或硅酸鹽水泥,水泥強(qiáng)度等級不低于P.O42.5,砂中含泥量3%,泥塊含量1%,石中的含泥量1%,泥塊含量0.5%。水泥不得與80以上的水直接接觸。 c、水泥、防凍劑有出廠質(zhì)量證明書等質(zhì)量證明文件,并有復(fù)試試驗報告。為減少凍害,盡量降低砼中水的用量,每立方中水泥的含量不得低于300Kg,水灰比小于0.6,砼的攪拌時間比常溫延長50%。 d、為加快拆模時間,提高砼的早期強(qiáng)度,減少凍害,在砼中加入早強(qiáng)型復(fù)合防凍劑,摻量由攪拌站通過試配確定,但配制與加入防凍劑,應(yīng)設(shè)專人負(fù)責(zé)并做好記錄,嚴(yán)格按劑量要求摻入。 e、砼運到現(xiàn)場后不得低于10,入模溫度不得低于5,如發(fā)現(xiàn)砼溫度過低或已遭凍結(jié),
32、則作為廢品退回攪拌站。6.3.2 砼攪拌 a、攪拌砼時,骨料中不得帶有冰、雪及凍團(tuán)。 b、拌制摻用防凍劑的砼,當(dāng)防凍劑為粉劑時,可按要求摻量直接與水泥同時投入;當(dāng)防凍劑為液體時,先配制成規(guī)定濃度溶液,然后再根據(jù)使用要求,用規(guī)定濃度溶液再配制成施工溶液。各溶液分別置于明顯標(biāo)志的容器內(nèi),不得混淆,每班使用的外加劑溶液一次配成。 c、砼的運輸過程是導(dǎo)致熱量損失最關(guān)鍵的階段。因此,必須加快運輸速度,降低周轉(zhuǎn)次數(shù)。途中的熱量損失不能降低的過快,要求每小時不能超過45,同時運輸?shù)焦さ貢r,砼出機(jī)時溫度不低于10,砼入模溫度不低于5。因此,攪拌站應(yīng)合理確定砼的出罐溫度,并將各種環(huán)節(jié)的熱量損失考慮進(jìn)去。項目部做
33、好協(xié)調(diào)工作。6.3.3 對商砼站混凝土運輸車的要求(1) 混凝土運輸車要做保溫。(2) 罐車進(jìn)場后及時安排澆筑,避免停留時間過長而造成溫度降低或離析現(xiàn)象。6.3.4 砼的澆筑(1) 砼澆筑前將鋼筋、模板上的霜凍、冰雪等清理干凈。(2) 砼運到作業(yè)面以后,快鋪料、快振搗、快抹平,并及時覆蓋塑料薄膜和保溫被。盡量減少作業(yè)面,降低砼暴露的時間和面積,將熱量損失降低到最低限度。(3) 施工縫的留置符合設(shè)計和施工技術(shù)方案的要求,下次澆筑時,接縫處的砼強(qiáng)度不小于4Mpa。6.3.5 砼的保溫、養(yǎng)護(hù)措施針對該工程施工的主體部位,從施工質(zhì)量、施工工期、施工費用三方面綜合考慮,本工程砼的保溫養(yǎng)護(hù)采取砼拌制中摻加
34、早強(qiáng)型的防凍劑;施工過程中砼在澆筑完畢后隨即抹平,然后覆蓋一層塑料薄膜再覆蓋一層棉被。為了保證混凝土養(yǎng)護(hù)溫度,在構(gòu)筑物周圍用抗拉性強(qiáng)雙層彩條布,用采膠布包裹密封,并在室內(nèi)布置25-30個炭爐子生火加溫,形成暖棚。暖棚詳細(xì)做法:(1)將雙層懸掛在主體結(jié)構(gòu)周圍。同時懸掛層數(shù)為2層。(2)室內(nèi)確保炭爐子24小時供熱,保證室內(nèi)底部溫度不低于5。(3) 室內(nèi)應(yīng)有一定的濕度(由實驗室測定),當(dāng)濕度不夠時,要向混凝土面灑水養(yǎng)護(hù)。折模過程中,及時對混凝土表面進(jìn)行覆蓋保溫養(yǎng)護(hù),以減少砼熱量損失。選用隔氣性能好的塑料薄膜一層、覆蓋棉氈、彩條布或棉被(氣溫驟變時增加覆蓋保溫材料的厚度和層數(shù),以達(dá)到保溫效果)。6.3
35、.6 砼試塊制作: 冬施期間砼試塊除按常溫施工規(guī)范規(guī)定要求留置外,增加不少于三組的與結(jié)構(gòu)同條件養(yǎng)護(hù)的試塊。同條件試件,一組用于檢驗受凍前的砼強(qiáng)度,以作為豎向結(jié)構(gòu)拆除模板、水平結(jié)構(gòu)撤出保溫的依據(jù);一組用于檢驗梁砼拆除支撐的強(qiáng)度;另一組同條件養(yǎng)護(hù)28天后再標(biāo)養(yǎng)28天進(jìn)行試壓,參與混凝土的評定。6.4 土方回填工程筏板和剪力墻施工完畢后進(jìn)行土方回填施工,基礎(chǔ)回填采取素土回填,素土回填對其冬期施工質(zhì)量的保證作如下要求: 6.4.1 填方前清除基底上的冰雪和保溫材料及其它雜物。 6.4.2 回填土采用素土分層回填,分層夯實,夯實系數(shù)不小于0.95,填土內(nèi)有機(jī)質(zhì)含量不超過5;當(dāng)氣溫低于-10時,不宜進(jìn)行回
36、填作業(yè)。6.4.3 冬期施工土方回填,不得采用凍砂塊或受凍的砂石做回填料。6.4.4 回填宜連續(xù)進(jìn)行并應(yīng)夯實,以免地基土或已填的素土受凍,對當(dāng)天回填面層采取覆蓋巖棉被保溫,防止過夜面層凍脹,第二天回填前如有凍結(jié)部位必須挖除后重新回填。人工夯實時,每層鋪筑砂石厚度不超過20cm,夯實厚度為15cm左右,機(jī)械回填時,每層鋪筑砂石厚度不超過25cm,夯實厚度為20cm左右。6.5 塔吊基礎(chǔ)保護(hù) 考慮本地冬季時間長,底面冰凍厚度較深,可能對塔吊基礎(chǔ)地基產(chǎn)生凍脹,導(dǎo)致塔吊基礎(chǔ)承載力受損,影響正常使用,在塔吊基礎(chǔ)上部采用300mm厚珍珠巖保溫材料進(jìn)行灌實保溫,上鋪彩條布并壓實,基礎(chǔ)側(cè)面回填砂夾石。6.6
37、冬施期對施工現(xiàn)場臨電要求 (1) 供電線路,不能埋地的一定要架空,室外的配電箱、電焊機(jī)和機(jī)械設(shè)備搭設(shè)防雨雪棚。值班電工經(jīng)常檢查現(xiàn)場電氣設(shè)備的接地,接零保護(hù)裝置是否靈敏有效。電氣設(shè)備采用雙重保護(hù)措施漏電保護(hù)和絕緣保護(hù),及時檢查電線絕緣是否良好,接頭是否包好,禁止電線浸泡在雨雪水中。 (2) 在潮濕和易觸及帶電體場所的照明電源不得大于24V;在特別潮濕的場所或金屬容器內(nèi)工作的照明電源電壓不得大于12V;手持燈的電源線不得使用塑料線。 (3) 塔吊司機(jī)上班前檢查機(jī)身是否帶電,漏電裝置是否靈敏有效,各種操作機(jī)構(gòu)是否靈活、安全可靠;塔司每次下班后,須關(guān)好駕駛室門窗,切斷配電箱內(nèi)電源開關(guān),關(guān)好箱門上好鎖。
38、(4) 遇大暴雨或五級以上強(qiáng)風(fēng)等惡劣天氣,停止起重吊裝作業(yè)。6.7 測溫要求與試塊的留置6.7.1 從11月15日開始大氣測溫,做好氣象預(yù)測,指定專人負(fù)責(zé),逐日按規(guī)定做好氣溫記錄,主要是最高最低氣溫記錄。6.7.2 定專人負(fù)責(zé)測溫工作,按規(guī)定進(jìn)行測溫記錄,每天測溫記錄報項目技術(shù)負(fù)責(zé)人,測溫同時檢查監(jiān)督覆蓋保溫情況及砼表面情況。 6.7.3 混凝土澆筑時入模溫度至關(guān)重要,它是控制整個結(jié)構(gòu)強(qiáng)度的重要手段, 必須跟蹤檢測全過程,為熱工計算提供依據(jù),具體要求: (1) 組織冬施測溫、試驗等人員的上崗培訓(xùn),并在進(jìn)入冬施前,對測溫人員組織技術(shù)培訓(xùn),學(xué)習(xí)其工作范圍內(nèi)的有關(guān)知識,明確職責(zé),經(jīng)考試合格后方準(zhǔn)上崗
39、工作。(2) 砼運送到現(xiàn)場后每車都要進(jìn)行測溫檢查。 (3) 摻用外加劑的砼養(yǎng)護(hù)溫度在砼強(qiáng)度未達(dá)到臨界強(qiáng)度以前,每2h測一次,達(dá)到受凍臨界強(qiáng)度之后,每隔6h測一次,再延續(xù)測溫不少于48h。 (4) 室外氣溫及周圍環(huán)境溫度每晝夜定時定點測溫四次(02、08、14、20點測溫)并測最高、最低溫度并記錄最高最低氣溫。 (5) 測溫時按編號順序進(jìn)行,仔細(xì)讀數(shù),記錄在測溫表中,測溫記錄不得作假。 (6) 測砼溫度時,測溫表應(yīng)與外界氣溫隔離,測溫表留置在測溫孔內(nèi)的 時間不小于3分鐘。測溫檢查項目及次數(shù)測 溫 檢 查 項 目次 數(shù)時 間出 罐 入 模 溫 度4/工作班澆筑砼時測試砼養(yǎng)護(hù)溫度(達(dá)到臨界強(qiáng)度以前)
40、12/工作班每隔2小時測溫砼養(yǎng)護(hù)溫度(強(qiáng)度達(dá)到臨界強(qiáng)度)4/工作班每隔6小時測溫大 氣 與 環(huán) 境 溫 度4/晝夜02、8、14、20點測溫并測最高最低溫度(7) 測溫點設(shè)在溫度變化大,易散失熱量,易遭凍結(jié)的部位,在平面上如下圖所示布置23個測孔,在斷面上每個測孔沿深度方向布置3個測點,分別固定在離表面10cm處、中心處及離底面10cm處,以測定表面溫度、中心溫度及底面溫度。注意事項: A、每個測溫探頭在埋設(shè)前,應(yīng)作測試檢查,并根據(jù)測點布置圖驚醒編號,對號入座 B、測溫探頭必須牢固綁扎在相應(yīng)位置橫向較粗的鋼筋的下側(cè),同時要保證測溫探頭與鋼筋絕緣隔離。C、澆筑混凝土?xí)r應(yīng)小心,避免使測溫探頭移位。
41、脫落或損壞。七、施工質(zhì)量要求7.1 外加劑選用質(zhì)量證明書、技術(shù)檢測單、產(chǎn)品說明書齊全的合格產(chǎn)品。外加劑使用前均應(yīng)試配。7.2 冬期施工各分項工程必須嚴(yán)格按照施工方案要求進(jìn)行施工,不得偷工減料,弄虛作假。冬施期間嚴(yán)格控制溫度,作好拌和物的溫度和組織材料及砼入模溫度的測量工作,作好記錄并整理歸入單位工程技術(shù)資料檔案。7.3 設(shè)專人測溫,詳細(xì)做好測溫記錄,整理歸檔。測溫人員同時負(fù)責(zé)檢查覆蓋保溫情況,發(fā)現(xiàn)異常及時通知有關(guān)人員采取有效措施。檢查測溫孔的布置是否具有代表性,位置數(shù)量符合要求,測溫孔預(yù)留測溫管。7.4 砼用砂、石必須符合規(guī)范標(biāo)準(zhǔn),且必須清潔、不得含有冰、雪、凍塊等物質(zhì),不得混有活性骨料或其他
42、有害雜質(zhì)。嚴(yán)格檢查砼表面是否受凍,如有受凍現(xiàn)象應(yīng)立即將受凍區(qū)剔除,用千瓦燈對受凍區(qū)域烘烤加熱到2后修補(bǔ),并加強(qiáng)保溫。7.5 施工過程中,必須嚴(yán)格執(zhí)行自檢、互檢、交接檢和專檢制度,凡是沒有嚴(yán)格執(zhí)行方案的工程,堅決不允許進(jìn)行下道工序。7.6 嚴(yán)格控制砼拆除保溫和拆模時間。當(dāng)溫度為-5-8時,拆模時間不小于48h;當(dāng)溫度為-8-12時,拆模時間不小于72h;拆模強(qiáng)度不小于4N/2,模板及混凝土表面的保溫覆蓋要及時有效。八、安全措施8.1 加強(qiáng)對職工進(jìn)行冬施安全宣傳教育工作,制定五防(防風(fēng)、防滑、 防凍、 防毒、防爆炸)安全措施,做好各級安全交底工作。8.2 大風(fēng)雪后,要對臨時用電、吊裝機(jī)械和垂直運輸
43、設(shè)備等進(jìn)行檢查,雪后及時清掃道路通道、馬道和各操作部位的冰雪。冬期施工做好防滑措施,停工后復(fù)工時各機(jī)械設(shè)備應(yīng)全面檢查合格后方可投入使用。8.3 在鋼筋焊接施工操作中嚴(yán)格執(zhí)行安全技術(shù)措施,加強(qiáng)焊工的安全教育,防止發(fā)生燒傷、觸電及火災(zāi)事故的發(fā)生。8.4 做好現(xiàn)場臨邊及洞口防護(hù)工作。保溫材料必須符合環(huán)保及消防(阻燃)要求,妥善保管。8.5 冬施前對職工進(jìn)行安全生產(chǎn)及防火教育,制定安全消防、文施環(huán)保責(zé)任制,并定期檢查。易燃物指定地點存放,并設(shè)專人管理,防止火災(zāi)。消防器材按平面圖布置存放,數(shù)量充足操作靈活。8.6 冬施期使用棉被到指定廠家購買。保溫材料集中管理。8.7 準(zhǔn)備好檢驗合格的消防器材,項目值班
44、人員對施工現(xiàn)場不定時抽查,以防意外發(fā)生。8.8 冬施前,冬施領(lǐng)導(dǎo)小組及有關(guān)人員對所有機(jī)電設(shè)備,進(jìn)行全面的技術(shù)、質(zhì)量檢查,對不符合質(zhì)量、安全要求的嚴(yán)禁使用。各種機(jī)械、運輸車輛進(jìn)入冬施后對其全面檢查,不得帶病工作。機(jī)動車輛保證輪胎氣壓正常,冰雪條件下車輛慢行。8.9 電器線路要按規(guī)定架設(shè)并有安全保護(hù)措施,大風(fēng)雪后及時檢修。8.10 施工廢水及時排除,防止結(jié)冰,保證下水道暢通。8.11 定期進(jìn)行冬施安全檢查,消除安全隱患。九、消防及環(huán)保措施9.1 生活區(qū)、辦公區(qū)等設(shè)施取暖采用電暖器,照明與采暖分路控制。電暖器經(jīng)過安全部門檢查,同意認(rèn)可,在使用中應(yīng)注意防火、防觸電。9.2 嚴(yán)格現(xiàn)場用火制度,凡施工用火
45、必須領(lǐng)取動火證,當(dāng)日有效,過期作廢。9.3 冬期結(jié)束及施工過程中掉落的材料及時清理,并集中處理,避免被風(fēng)吹走,污染環(huán)境。施工時做到活完料凈場地清。9.4 嚴(yán)格執(zhí)行動火申請審批制度,現(xiàn)場動火及電焊需安全人員檢查同意后施工,并簽發(fā)動火證。任何人不得私自亂接電源,冬施前由有關(guān)人員對建筑工人住房、辦公室進(jìn)行檢查,發(fā)現(xiàn)隱患及時處理。 9.5 工具房、材料庫內(nèi)一律不準(zhǔn)生火。油料、防水材料等易燃材料庫需遠(yuǎn)離火源。9.6 安全管理人員加強(qiáng)夜間巡查,發(fā)現(xiàn)隱患及時處理。9.7 雪后清掃積雪,有泥漿處應(yīng)清除,防止運輸車輛將泥漿帶上市政道路。運輸袋裝水泥、白灰和砂、石等其它易飛揚(yáng)的細(xì)顆粒散體材料及建筑渣土均需用彩條布
46、或苫布遮蓋嚴(yán)實,以防止揚(yáng)塵。9.8 施工場地的準(zhǔn)備工作:1) 排除現(xiàn)場積水、淤泥,對施工現(xiàn)場進(jìn)行必要的修整,截斷流入現(xiàn)場的水源,做好排水措施,消除現(xiàn)場施工用水造成場地結(jié)冰現(xiàn)象。2) 施工場地積雪清掃后,不得堆放在機(jī)電設(shè)備、構(gòu)件堆放場地附近。 3) 保證消防道路的暢通。4)上水管、閥門井、消火栓井應(yīng)做好保溫。十、 冬施期保溫材料的準(zhǔn)備10.1混凝土表面覆蓋保溫材料:選用隔氣性能好的塑料薄膜一層、覆蓋棉氈、彩條布或草簾子(氣溫驟變時增加覆蓋保溫材料的厚度和層數(shù),以達(dá)到保溫效果)并在建筑物周邊用鋼管搭設(shè)封閉式暖棚,棚內(nèi)用柴油爐子加溫。材料計劃表詳見5.3.3 10.2考慮到冬施期日工作時間短和砼強(qiáng)度
47、增長較慢,為確保在規(guī)定的冬施期內(nèi)完成以上工作任務(wù),筏板、剪力墻施工在現(xiàn)有一個流水段模板配置的基礎(chǔ)上,計劃再增加一個流水段的模板,以滿足施工需要。另由于需要搭設(shè)暖棚,相關(guān)增加的材料詳見下表冬施模板及配件增加材料表序號材料名稱單位數(shù)量備注148鋼管米30002扣件個25503木方(50×100)m3904竹膠合板(12mm厚)m2150010.3冬施期間的人員安排:根據(jù)冬施特點并考慮到人工降效的影響,需在現(xiàn)有人員的基礎(chǔ)上增加部分冬施人員詳見下表冬施增加人員表序號工種增加人數(shù)備注1測溫人員43保溫設(shè)施搭設(shè)、拆除與維護(hù)人員84木工195鋼筋工166普工167保衛(wèi)人員4十一、冬季施工砼的熱工計
48、算11.1 蘭州地區(qū)室外溫度不小于-15時,采用蓄熱法施工、負(fù)溫養(yǎng)護(hù)法,只需要重點計算混凝土是否能滿足冬施要求即可。根據(jù)建筑施工手冊19-2-6,在混凝土摻入防凍劑后,混凝土出機(jī)溫度不得低于10,入模溫度在5以上;計算中室外的氣溫按常年取其-15。但是為了保證混凝土的質(zhì)量,要求商砼公司出具冬期混凝土質(zhì)量保證方案,確保所有混凝土的出機(jī)溫度必須大于或等于10。現(xiàn)計算混凝土拌合物入模溫度T2,運輸時間45min,澆筑時間15min公式為:T2=T1-(att+0.032n)(T1-Ta)公式中:.T1混凝土拌合物的出機(jī)溫度,取T1=15.T2混凝土拌合物經(jīng)攪拌車運輸至泵車的溫度().a 溫度損失系數(shù)
49、 當(dāng)用混凝土攪拌車運輸時,a=0.25.tt混凝土自運輸至澆筑成型完成的時間(H),tt=1h(運輸時間45min,澆筑時間15min).Ta運輸時的環(huán)境氣溫().n混凝凝土轉(zhuǎn)運次數(shù),n=2次.T2=T1-(att+0.032n)(T1-Ta)=15-(0.25×1+0.032×2)15-(-15)=5.585 滿足要求此溫度高于入模溫度,滿足不得低于5的規(guī)定。11.2當(dāng)室外溫度小于-15時,不允許采用綜合蓄熱法、負(fù)溫養(yǎng)護(hù)法。需要依據(jù)6.3.5使用棚罩式封閉加溫保證溫度在棚內(nèi)溫度不低于5。綜上分析計算可得出:商品砼拌合物的出機(jī)溫度及運至施工現(xiàn)場的入模溫度完全符合混凝土結(jié)構(gòu)工
50、程施工質(zhì)量驗收規(guī)范GB50204國家標(biāo)準(zhǔn)與建筑工程冬期施工規(guī)程(JGJ/T104-2011)的要求。十二、應(yīng)急預(yù)案應(yīng) 急 預(yù) 案1、 應(yīng)急預(yù)案工作流程圖根據(jù)本工程的特點及該季冬期施工工藝的實際情況,項目部認(rèn)真組織了對危險源和環(huán)境因素的識別和評價,特制定本項目發(fā)生緊急情況或事故的應(yīng)急措施,開展應(yīng)急知識教育和應(yīng)急演練,提高現(xiàn)場操作人員應(yīng)急能力,減少突發(fā)事件造成的損害和不良環(huán)境影響。其應(yīng)急準(zhǔn)備和響應(yīng)工作程序見下圖:(圖1 應(yīng)急準(zhǔn)備和響應(yīng)工作程序圖)危險源及環(huán)境因素辯識、評價編制應(yīng)急預(yù)案成立搶險領(lǐng)導(dǎo)小組組建搶險隊、救護(hù)車配備應(yīng)急物資、設(shè)備應(yīng)急知識教育培訓(xùn)定期評審實施應(yīng)急預(yù)案進(jìn)行評審、修訂未發(fā)生發(fā)生2、
51、 突發(fā)事件、緊急情況風(fēng)險分析與預(yù)防措施為確保正常施工,預(yù)防突發(fā)事件以及某些預(yù)想不到的、不可抗拒的事件發(fā)生,事前有充足的技術(shù)措施準(zhǔn)備、搶險物資的儲備,最大程度地減少人員傷亡、國家財產(chǎn)和經(jīng)濟(jì)損失,必須進(jìn)行風(fēng)險分析和預(yù)防。、突發(fā)事件、緊急情況及風(fēng)險分析根據(jù)本工程冬期施工特點及復(fù)雜的地質(zhì)情況,在辯識、分析評價施工中危險因素和風(fēng)險的基礎(chǔ)上,確定本工程重大危險因素是突發(fā)火災(zāi)、寒凍、觸電、物體打擊、高處墜落等。、突發(fā)事件及風(fēng)險預(yù)防措施從以上風(fēng)險情況的分析看,如果不采取相應(yīng)有效的預(yù)防措施,不僅給基礎(chǔ)施工造成很大影響,而且對施工人員的安全造成威脅。A、筏板、剪力墻施工前應(yīng)按冬施方案中計劃的材料表進(jìn)行防寒凍材料儲
52、備購置,以確保砼澆筑后進(jìn)行有效的覆蓋保溫養(yǎng)護(hù),保證該工程冬期施工質(zhì)量。B、材料準(zhǔn)備:材料儲備購置中,應(yīng)比計劃表中數(shù)目略超10%,以備使用。C、為防止出現(xiàn)施工作業(yè)區(qū)和工人宿舍內(nèi)工人不安全用電與取暖行為導(dǎo)致的人員中毒、觸電和突發(fā)火災(zāi)事件,項目部應(yīng)組織冬施期安全檢查領(lǐng)導(dǎo)小組(領(lǐng)導(dǎo)小組成員同現(xiàn)場應(yīng)急救援領(lǐng)導(dǎo)小組人員,附后)進(jìn)行每天早、中、晚定時與不定時安全檢查,一旦發(fā)現(xiàn)安全隱患,立即整改。D、執(zhí)行現(xiàn)場施工用電規(guī)定,非專業(yè)人員禁止動用機(jī)電設(shè)備,現(xiàn)場電工要經(jīng)常檢查供電線路、閘箱、機(jī)電設(shè)備的完好和絕緣情況,供電線路要架空,防止機(jī)械碰壓。現(xiàn)場電工負(fù)責(zé)安裝臨時用移動配電箱與開關(guān)箱,全力負(fù)責(zé)臨時接用電并負(fù)用電安全職責(zé),避免發(fā)生其他人員亂用電而導(dǎo)致觸電事故發(fā)生。E、下雪天過后,要及時清理塔機(jī)爬梯上的積雪,以防塔司作業(yè)上機(jī)過程中墜落摔傷。3、應(yīng)急事故發(fā)生處理流程圖:一旦出現(xiàn)人員中毒或受傷、突發(fā)火災(zāi)、觸電、物體打擊、高處墜落等事故時應(yīng)立即起動應(yīng)急救援預(yù)案。現(xiàn)場管理人員根據(jù)出現(xiàn)的險情或有可能出現(xiàn)的險情,迅速逐級上報,次序為現(xiàn)場、辦公室、搶險救援領(lǐng)導(dǎo)小組、上級主管部門。由施工第一線收集、記錄、整理緊急情況信息并向小組及時傳遞,由小組組長或副組長主持緊急情況處理會議,協(xié)調(diào)、派遣和統(tǒng)一指揮現(xiàn)場所有車輛、設(shè)備、人員、物資等實施緊急搶救和向上級匯報。事故處理根據(jù)事故大小情況來確定,如果事故特別小,根據(jù)上
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 中華優(yōu)傳統(tǒng)文化 課件 第三章 中國傳統(tǒng)思維方式
- 2025貴州農(nóng)業(yè)職業(yè)學(xué)院輔導(dǎo)員考試試題及答案
- 2025蘇州工業(yè)園區(qū)職業(yè)技術(shù)學(xué)院輔導(dǎo)員考試試題及答案
- 捷克旅游線路設(shè)計方案
- T/YNIA 009-2022隔離衣用非織造布
- 2025年主持與播音考試模擬題及答案
- 人文創(chuàng)意產(chǎn)業(yè)考試題及答案2025年
- 2025年學(xué)習(xí)動機(jī)與策略發(fā)展基礎(chǔ)知識考試試題及答案
- 2025年土木工程材料綜合檢測學(xué)習(xí)考試試題及答案
- 2025年市場調(diào)研師考試試卷及答案
- 2025年山東省聊城市高唐縣中考二模英語試題(原卷版+解析版)
- 企業(yè)數(shù)字化轉(zhuǎn)型培訓(xùn)課件
- 2025屆高考語文押題作文及題目(9篇)
- 2025年中國白楊樹市場現(xiàn)狀分析及前景預(yù)測報告
- 中共中央辦公廳、國務(wù)院辦公廳關(guān)于進(jìn)一步穩(wěn)定和完善農(nóng)村土地承包關(guān)系的通知中辦發(fā)〔1997〕16號,1997年6
- 計算機(jī)應(yīng)用基礎(chǔ)-終結(jié)性考試試題國開要求標(biāo)準(zhǔn)
- 預(yù)制梁場驗收及質(zhì)量管理實施細(xì)則
- 鞋業(yè)訂貨單模版
- 大理石打磨工程裝飾協(xié)議合同
- 模塊化低壓配電柜MODAN6000樣本_圖文
- 國有資產(chǎn)管理情況整改報告
評論
0/150
提交評論